Agenda item
Development of SEN Provision at Hay Lane and Grove Park Sites -The Village School including award of Design and Build contract
This report summarises the procurement process undertaken by the Council to procure a Design & Build contractor for the temporary accommodation at The Village School and provides an update on the award of the contract for the appointment of a Design and Build contractor for that temporary accommodation.
Decision:
that the Design and Build Contract for the main works for The Village School be awarded to JB Leadbitter & Co Ltd, trading as Leadbitters, in the sum of £18,856,721.00.
Minutes:
The Director of Regeneration and Major Projects Council introduced his report which summarised the process to procure a Design and Build contractor for the temporary accommodation at The Village School, NW9. The Director advised that work on the temporary accommodation had commenced earlier in the day. The Director’s report also summarised the procurement process undertaken by the council to procure a Design and Build contractor for the main works contract and requested authority to award the contract for the appointment of a Design and Build contractor for this scheme. He was pleased to report that the contract sum was within the estimated project costs.
The Executive also had before it appendices to the report which were not for publication as they contained the following category of exempt information as specified in Paragraph 3 of Schedule 12A to the Local Government Act 1972, namely:
Information relating to the financial or business affairs of any particular person (including the authority holding that information).
RESOLVED:-
that the Design and Build Contract for the main works for The Village School be awarded to JB Leadbitter and Co Ltd, trading as Leadbitters, in the sum of £18,856,721.00.
Supporting documents:
- tvs, item 15. PDF 102 KB
- tvs-app1, item 15. PDF 25 KB
- tvs-app2, item 15. PDF 65 KB
- tvs-app5, item 15. PDF 20 KB
- tvs-app6, item 15. PDF 2 MB
- Restricted enclosure View the reasons why document 15./6 is restricted
- Restricted enclosure View the reasons why document 15./7 is restricted
- Restricted enclosure View the reasons why document 15./8 is restricted