20 South Kilburn regeneration acquisition of additional land PDF 647 KB
This report provides an update of progress of the regeneration of South Kilburn since the Report to the Executive meeting on 23rd June 2010. It also seeks member’s decisions for a range of items in order to progress the regeneration objectives for the South Kilburn estate.
Appendices also below
Additional documents:
- PINK-rmp-sth-kilburn-rpt-append 1 , View reasons restricted (20/2)
- rmp-sth-kilburn-background-paper-1a-june10, item 20 PDF 201 KB
- PINK-rmp-sth-kilburn-background-paper-1b-june-app2 , View reasons restricted (20/4)
- rmp-sth-kilburn-background-paper-2-july09-map-legend-app2, item 20 PDF 2 MB
- rmp-sth-kilburn-background-paper-3a-july09, item 20 PDF 176 KB
- PINK-rmp-sth-kilburn-background paper-3b-july09-app2 , View reasons restricted (20/7)
Decision:
(i) that progress of regeneration and the clarifications to the phasing plan for the regeneration of the South Kilburn estate, and that work is proceeding to update this phasing plan be noted;
(ii) that the immediate cessation of permanent lettings on the properties at Bond House, Cambridge Court, Ely Court, Bronte House, Fielding House, Hicks Bolton House, Wells Court and Wood House be authorised;
(iii) that agreement be given to the service of demolition notices in relation to secure tenancies at Bond House, Bronte House, Cambridge Court, Ely Court, Fielding House, Hicks Bolton House, Wells Court and Wood House, which are all on the South Kilburn estate, and the Director of Housing and Community Care be authorised to issue all and any notices required to be issued in connection with such demolition;
(iv) that the Director of Housing and Community Care be authorised to carry out the prescribed statutory consultation procedure and seek the Secretary of State’s consent to the phased disposal and redevelopment of Bronte House, Fielding House, Wells Court and Wood House in addition to the Phase 1 sites on the South Kilburn estate referred to in paragraph 3.26 of the report from the Director of Regeneration and Major Projects for the purposes of Ground 10A of Schedule 2 to the Housing Act 1985 to enable the Council to apply for a court order to obtain vacant possession of those residential dwellings let under secure tenancies.
(v) that the following be authorised:
(a) the making of compulsory purchase orders (the CPO’s) to acquire all interests and rights in the properties listed in appendix 1 [and otherwise comprised in the land edged in bold black and hatched on the draft Plan headed [the map referred to in the London Borough of Brent South Kilburn Regeneration Compulsory Purchase Order 2010-11] inclusive of the leasehold interests set out on Appendix 2 to the Report to the Executive meeting on 23 June 2010 being interests in the South Kilburn estate which properties are referred to hereafter as “the CPO Land” under section 226 (1)(a) of the Town and Country Planning Act 1990 and any new rights in the CPO Land which may be required under section 13 of the Local Government (Miscellaneous Provisions) Act 1976;
(b) the Director of Housing and Community Care in consultation with the Director of Legal and Procurement to include in the Compulsory Purchase Orders authorised by the Executive on 23 June 2010 and at this Executive meeting such other additional interests and rights as are disclosed during the land referencing exercise which the Director of Regeneration and Major Projects in consultation with the Director of Housing and Community Care and the Director of Legal and Procurement deem it necessary to facilitate the delivery of the South Kilburn Regeneration Phase 1;
(vi) that the CPOs, once made, be submitted to the Secretary of State for confirmation whilst at the same time seeking to acquire the land by private negotiated treaty on such terms as may be ... view the full decision text for item 20
Minutes:
Councillor Crane (Lead Member, Regeneration and Economic Development) introduced the report which provided an update of progress of the regeneration of South Kilburn since the report to the Executive meeting on 23 June 2010. It also sought members’ agreement to a range of items in order to progress the regeneration objectives for the South Kilburn estate. Councillor Crane drew attention to the financial implications set out in the report in particular the sale of land and using the capital receipt progress to further sites. He also pointed out the possibility of current central government cuts impacting on the Homes and Communities Agency which would affect programme funding.
RESOLVED:-
(i) that progress of regeneration and the clarifications to the phasing plan for the regeneration of the South Kilburn estate, and that work is proceeding to update this phasing plan be noted;
(ii) that the immediate cessation of permanent lettings on the properties at Bond House, Cambridge Court, Ely Court, Bronte House, Fielding House, Hicks Bolton House, Wells Court and Wood House be authorised;
(iii) that agreement be given to the service of demolition notices in relation to secure tenancies at Bond House, Bronte House, Cambridge Court, Ely Court, Fielding House, Hicks Bolton House, Wells Court and Wood House, which are all on the South Kilburn estate, and the Director of Housing and Community Care be authorised to issue all and any notices required to be issued in connection with such demolition;
(iv) that the Director of Housing and Community Care be authorised to carry out the prescribed statutory consultation procedure and seek the Secretary of State’s consent to the phased disposal and redevelopment of Bronte House, Fielding House, Wells Court and Wood House in addition to the Phase 1 sites on the South Kilburn estate referred to in paragraph 3.26 of the report from the Director of Regeneration and Major Projects for the purposes of Ground 10A of Schedule 2 to the Housing Act 1985 to enable the Council to apply for a court order to obtain vacant possession of those residential dwellings let under secure tenancies.
(v) that the following be authorised:
(a) the making of compulsory purchase orders (the CPO’s) to acquire all interests and rights in the properties listed in appendix 1 [and otherwise comprised in the land edged in bold black and hatched on the draft Plan headed [the map referred to in the London Borough of Brent South Kilburn Regeneration Compulsory Purchase Order 2010-11] inclusive of the leasehold interests set out on Appendix 2 to the Report to the Executive meeting on 23 June 2010 being interests in the South Kilburn estate which properties are referred to hereafter as “the CPO Land” under section 226 (1)(a) of the Town and Country Planning Act 1990 and any new rights in the CPO Land which may be required under section 13 of the Local Government (Miscellaneous Provisions) Act 1976;