Decision details
The Community Infrastructure Levy Draft Charging Schedule and the Section 106 Planning Obligations Supplementary Planning Document
Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To consider and note the contents of the Community Infrastructure Levy Draft Charging Schedule and the Section 106 Planning Obligations SPD.
Decision:
(i) that approval be given to the Director of Regeneration & Major Projects formally consulting on the Preliminary Draft Community Infrastructure Levy Charging Schedule;
(ii) that approval be given to the Director of Regeneration & Major Projects formally consulting on the S106 Planning Obligations Supplementary Planning Document;
(iii) that the proposals to increase member and community involvement in the spending of monies secured through S106 Planning Obligations and the Community Infrastructure Levy, and locate internal management arrangements for expenditure on infrastructure to support major projects and growth within the New Initiatives Team be noted.
Wards Affected: (All Wards);
Other reasons / organisations consulted
Wembley Project Board. External consultation following approval of the document in accordance with The Town and Country Planning (Local Development) (England) (Amendment) Regulations 2008. The regulations require the council to consult statutory consultees and local residents/ businesses who have an interest in the Area Action Plan.
Contact: Dave Carroll, Planning and Development Email: dave.carroll@brent.gov.uk Tel: 020 8937 5202.
Report author: Dave Carroll
Publication date: 19/10/2011
Date of decision: 17/10/2011
Decided at meeting: 17/10/2011 - Executive
Accompanying Documents: