Authority to trigger stage 2 Design and Build Contracts in relation to Phase 3 Primary School Expansion Programme
To... 1. trigger the Stage 2 Design and Build
Contracts with Graham Construction for the Phase 3 Primary School
Expansion Programme at Byron Court Primary School in the sum of
£ 11,872,271. 2. trigger the Stage 2 Design and Build
Contracts with Mid Contracting and Consulting Limited for the Phase
3 Primary School Expansion Programme at Stonebridge Primary School
in the sum of £ 7,222,848. 3. trigger the Stage 2 Design and
Build Contracts with Lakehouse Contracts Ltd for the Phase 3
Primary School Expansion Programme at Uxendon Manor Primary School
in the sum of £ 6,784,436.
Decision type: Key
Decision status: Recommendations Approved
Notice of proposed decision first published: 11/09/2017
Anticipated restriction: Part exempt - View reasons
Decision due: 11 Sep 2017 by Strategic Director - Regeneration and Environment
Department: Regeneration and Environment
Contact: Amar Dave, Strategic Director Regeneration and Environment Email: Amar.Dave@brent.gov.uk Tel: 0208 937 1516.
Member/s' declarations of interest /: Provide details of any declarations of interest by Lead Member(s)/Committee Chairman consulted by the officer. If relevant, please make a note of the dispensation granted by the Monitoring Officer: N/A.
Highlight any associated risks/finance/legal/equality considerations: Please refer to the accompanying officer report.
Decisions
- 11/09/2017 - Authority to trigger stage 2 Design and Build Contracts in relation to Phase 3 Primary School Expansion Programme
Background papers