Decision details
Authority to vary a contract in respect of the Design and Build Contract for the London Road SEND School with Reds 10 (UK) Ltd (non-key officer recordable decision)
Decision Maker: Corporate Director of Neighbourhoods & Regeneration
Decision status: For Determination
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To request authority to vary a contract in respect of the London Road SEND School Design and Build Contract with Reds10 (UK) Ltd.
Decision:
That the Corporate Director Neighbourhoods and Regeneration:
i) Approves the variation of the contract for the London Road SEND School Design and Build Contract with Reds10(UK) Ltd as follows:
(a) Increase the value of the two-stage Design and Build Contract to £22,204,085.34 (variation of £276,589.11).
(b) Agree the final account for the Main Works contract.
Reasons for the decision:
The Council entered into a two-stage design and build contract for the design and build of London Road SEND School with Reds10(UK) Ltd on 15 March 2023. The value of the contract, including both the Pre-Construction Services Agreement (PCSA) and Main Works contract was £21,927,496.23.
Officers have concluded that the contract needs to be varied to increase the value of the contract to £22,204,085.34.
The increase relates to changes to scope and requirements during both the PCSA and the Main Works contract. These changes were necessary to complete the design of the school, conduct enabling works to the sewer on site as well as ensuring the doors proposed meet the needs of the school.
Alternative options considered:
Officers have considered alternative proposals to varying the contract, such as seeking alternative contractors to complete the variation works. This was discounted due to the time it would take to design the requirements and procure a contractor.
A do nothing option was considered, but this would mean the school would not be able operate appropriately and would risk safeguarding and security needs specific to SEND children. This option was therefore discounted.
Cabinet/Committee Decision or Scheme of Delegation: Officer scheme of delegation - non-key recordable officer decision.
Parties Consulted: The Cabinet Member for Regeneration and Planning has been consulted on the report and confirmed they are content for the Corporate Director to make the decision to vary the contract with Reds10 (UK) Ltd. Ward members, local residents and the school and its Academy Trust are kept up to date with progress on the project.
Contact: Neil Martin, Head of Capital Delivery Email: neil.martin@brent.gov.uk Tel: 020 8937 4203.
Publication date: 13/10/2026
Date of decision: 12/10/2026