Authority to Vary the Contract and Approve the Final Account with Hill Partnerships Ltd for the Watling Gardens Design and Build Contract (non-key recordable officer decision)

  • Find out more about this issue

Decision Maker: Director - Inclusive Regeneration and Climate Action

Decision status: Recommendations Approved

Is Key decision?: No

Is subject to call in?: No

Purpose:

To request approval to vary the Design and Build Contract with Hill Partnerships Ltd to deliver the Watling Gardens project, and to confirm the final account for the contract.

Decision:

The Director of Inclusive Regeneration and Climate Action:

 

i)               Approves the variation of the Design and Build Contract with Hill Partnerships Ltd for the delivery of the Watling Gardens project by £321,842.68 to undertake necessary variations including repairs to the estates boundary wall to minimise health and safety risk, changes to flooring materials in Block C, requirement for fully automated doors in Block C, wet room adaptations, block B external works, additional white goods, changes to laundry room and additional security requirements.

 

ii)              Approves the final account of the Design and Build Contract with Hill Partnerships Ltd for the delivery of the Watling Gardens project.

Reasons for the decision:

The Council entered into a Design and Build Contract with Hill Partnerships Ltd for the delivery of the Watling Gardens project on 8 November 2022. The project achieved practical completion on 6 February 2026. In achieving this milestone, there have been a number of variations to the contract.

 

To this end, officers are seeking approval to vary the contract to meet these additional changes and consequently agree the final contract account.

Alternative options considered:

The proposal is to agree the additional changes to the existing contract with Hill Partnerships Ltd. An alternative option would be for the Council to not proceed with the additional requirements and seek alternative contractors. This has been discounted due to the time it would take to procure new contractors and the efficiencies of utilising the incumbent provider.

Interests and Nature of Interests Declared:

None.

Wards Affected: Cricklewood & Mapesbury;

Cabinet/Committee Decision or Scheme of Delegation: officer scheme of delegation - non-key officer recordable decision

Parties Consulted: The Council delivered quarterly resident panel meetings throughout the construction works, including more frequent tailored meetings for specific works. Officers are exploring options with the communications team for an official opening event.

Contact: Jas Yembra, Capital Project Manager, Special Projects - Schools Email: jas.yembra@brent.gov.uk Tel: 020 8937 2379.

Publication date: 05/08/2026

Date of decision: 05/08/2026

 

Navigation

  • Decision - Authority to Vary the Contract and Approve the Final Account with Hill Partnerships Ltd for the Watling Gardens Design and Build Contract (non-key recordable officer decision)
  • What's new
  • Committees
  • Constitution
  • Calendar
  • Meetings
  • Committee decisions
  • Officer Decisions
  • Forward plans
  • Your Councillors
  • Your MPs
  • Election Results
  • Outside bodies
  • Search documents
  • Subscribe to updates
Brent homepage
Your council
Complaints and feedback Contact the council Jobs at the council News and Press office Sign up to our weekly email news updates
My Account
Manage your Council Tax, housing benefits, council rent account and more through My Account.
Sign in or register
Follow us on social
Brent Council's Facebook page Brent's Instagram page Brent Council's LinkedIn site Brent council's Twitter feed Brent council's YouTube channel
Accessibility statement Cookies policy Privacy policy Terms of use
© Copyright Brent Council 2022

Title