Decision details
Authority to procure a contractor under a Framework Agreement to design and build the SEND provision at the Woodfield School (Non-Key Officer Recordable Decision)
Decision Maker: Director - Property and Assets
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Purpose:
To request approval to use a framework to procure a contractor for the expansion of the Woodfield School.
Decision:
That the Director of Property and
Assets:
i) Approves Brent Council’s participation in a call-off procedure under the Crown Commercial Service (CCS) Offsite Construction Solutions Framework Agreement (RM6184) in respect of a design and build contract for the expansion of the Woodfield School.
ii) Confirms that there is sufficient budgetary provision for the proposed call-off contract.
iii) Approves inviting bids under the Framework Agreement referred to in 2.1 for the Woodfield School contractor on the basis of the pre – tender considerations.
iv) Approves Officers evaluating bids on the basis of the evaluation criteria.
Reasons for the decision:
To procure a contractor by way of a
mini-competition under the Crown Commercial Service (CCS) Offsite
Construction Solutions Framework Agreement (RM6184) in respect of
the design and build contract for Woodfield School.
The Council is proposing to appoint a contractor using this
framework as it allows access to economical build rates by
procuring a single contractor for both Schools.
Alternative options considered:
Officers have reviewed a range of procurement options including conducting a tender process but have concluded that the use of the Framework is the most appropriate means of procuring a contractor given the reduction in time-scales, costs and resources involved.
Cabinet/Committee Decision or Scheme of Delegation: Officer scheme of delegation - non-key officer recordable decision.
Parties Consulted: The Cabinet Member for Children, Young People and Schools has been consulted on the SEND Capital Programme progress and these specific projects. Ward members will be kept up to date with project progress, such as planning application submissions and works starting onsite. The school has been a key stakeholder during the project's deisgn and progress and will continue to be involved as the contract progresses.
Contact: Tanveer Ghani, Director - Property and Assets Email: tanveer.ghani@brent.gov.uk Tel: 020 8937 1722.
Publication date: 05/06/2025
Date of decision: 05/06/2025