Decision details
Air quality improvement measures: Electric vehicle charging infrastructure – Cabinet variation report
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To agree a variation to the procurement
process for the project to deliver on-street residential charge
points in lamp columns,
Decision:
RESOLVED:-
8.1 That Cabinet notes the reason as set out in paragraph 4.2 as to why the procurement process in respect of the supply, installation, maintenance and operation of charge points in lamp columns for electric vehicles on residential streets in Brent cannot proceed as agreed by Cabinet on 15 January 2018;
8.2 That Cabinet approves the procurement of the supply, installation, maintenance and operation of charge points in lamp columns for electric vehicles on residential streets in Brent from TfL’s Electric Vehicle Charging Infrastructure Framework Agreement; and
8.3 that Cabinet delegates authority to the Strategic Director Regeneration and Environment, in consultation with the Lead Member for Environment, to authorise an alternative procurement process for the supply, installation, maintenance and operation of charge points in lamp columns for electric vehicles should the TfL Electric Vehicle Charging Infrastructure Framework Agreement be delayed in its set up or fail to address Brent Council’s needs for the reasons set out in paragraph 4.9.
Reason Key: Affects more than 2 wards;
Wards Affected: (All Wards);
Contact: Grace Eminton, Transport Planner Email: grace.eminton@brent.gov.uk Tel: 0208 937 5245.
Report author: Grace Eminton
Publication date: 04/07/2018
Date of decision: 18/06/2018
Decided at meeting: 18/06/2018 - Cabinet
Accompanying Documents: