Decision to delegate authority for the award of contract for a delivery partner for Peel Project, and for approval to amend red line and for appropriation for the Peel Site

  • Find out more about this issue

Decision Maker: Cabinet

Decision status: Recommendations Approved

Is Key decision?: Yes

Is subject to call in?: Yes

Purpose:

This report seeks:
(i) approval to the amendments to the red line boundary for the Peel site

(ii) approval to authorise the Strategic Director of Regeneration and Environment in consultation with the Lead Member Regeneration, Growth, Employment and Skills to award a contract for a Delivery Partner for the “Peel” site within the South Kilburn Regeneration Programme

(iii) approval to advertise the Council’s intention to appropriate and thereafter dispose of open space

(iv) to appropriate the whole site including open space for planning purposes

(v) To update on progress since the original approvals were given and seek approval and re-affirmation of the original decision to proceed with the CPO.

Decision:

It was RESOLVED:

 

22.1    That the original approvals given in the resolutions made on 11 November 2013 authorising the making and implementation of a compulsory purchase order ("CPO") to further the redevelopment of the Peel Site (as previously documented under the headings 'Peel Recommendations' and 'CPO Recommendations' at paragraph 16 of the Minutes of the Executive meeting held on 11 November 2013, be reaffirmed;

 

22.2    That the previous Executive and Cabinet decisions as detailed in paragraph 3.5 of the report to utilise Ground 10A of the Housing Act 1985 (if approval is given by the Secretary of State) and compulsory purchase powers under section 226(1)(a) of the Town and Country Planning Act 1990 to secure the vacant possession of properties within the Peel, be reaffirmed; 

 

22.3    That the new red line boundary for the Peel site as shown on the plan at appendix 1, be approved;

 

22.4    That authority be delegated to the Strategic Director of Regeneration and Environment in consultation with the Lead Member Regeneration, Growth, Employment and Skills to award a contract for a Delivery Partner for the Peel site for the reasons detailed in paragraph 3.8 of the report following the OJEU procurement process;

 

22.5    That the advertisement of the Council’s intention to appropriate the open space (shown at appendix 2) in accordance with its powers under section 122 of the Local Government Act 1972 and dispose of open space at the Site to a third party in accordance with the provisions of section 233 of the Town and Country Planning Act 1990, be approved;

 

22.6    That authority be delegated to the Strategic Director of Regeneration and Environment, in consultation with the Lead Member for Regeneration, Growth, Employment and Skills, to consider the representations made by the public in response to the advertisement to appropriate and dispose of the open space and thereafter to decide whether to appropriate and dispose of the open space;

 

22.7    That authority be delegated to the Strategic Director of Regeneration and Environment in consultation with the Lead Member for Regeneration, Growth, Employment and Skills to Appropriate the open space at the Peel  Site, and appropriate and dispose of the whole Site including open space for planning purposes (shown at appendix 1) if the Strategic Director of Regeneration and Environment in consultation with the Lead Member for Regeneration, Growth, Employment and Skills decides to do so following the consultation; and

 

22.8    That the application to the Secretary of State by the Strategic Director of Regeneration and Environment to seek the Secretary of State’s consent under section 19 Housing Act 1985 to appropriate any part of the Site including any part consisting of a house or part of a house so that the Site is no longer held for the purpose of part II of the Housing Act 1985, be approved.

Wards Affected: Kilburn;

Contact: Jill Rennie, Senior Project Manager, Estate Regeneration Email: jill.rennie@brent.gov.uk Tel: 020 8937 2556.

Report author: Jill Rennie

Publication date: 13/02/2018

Date of decision: 12/02/2018

Decided at meeting: 12/02/2018 - Cabinet

Effective from: 20/02/2018

Accompanying Documents:

  • Decision to delegate authority for the award of contract for a delivery partner for Peel Project, and for approval to amend red line and for appropriation for the Peel Site pdf icon PDF 161 KB
  • Appendix 1 - Peel Red Line Plan pdf icon PDF 201 KB
  • Appendix 2 - Peel Open Space pdf icon PDF 201 KB
  • Appendix 3 - Peel Red Line Boundary pdf icon PDF 271 KB
  • Appendix 4 - Peel Red Line Boundary Adjustment pdf icon PDF 181 KB
  • Restricted enclosure  View reasons restricted
  • Appendix 6 - Peel Lease Extent pdf icon PDF 194 KB

 

Navigation

  • Decision - Decision to delegate authority for the award of contract for a delivery partner for Peel Project, and for approval to amend red line and for appropriation for the Peel Site
  • What's new
  • Committees
  • Constitution
  • Calendar
  • Meetings
  • Committee decisions
  • Officer Decisions
  • Forward plans
  • Your Councillors
  • Your MPs
  • Election Results
  • Outside bodies
  • Search documents
  • Subscribe to updates
Brent homepage
Your council
Complaints and feedback Contact the council Jobs at the council News and Press office Sign up to our weekly email news updates
My Account
Manage your Council Tax, housing benefits, council rent account and more through My Account.
Sign in or register
Follow us on social
Brent Council's Facebook page Brent's Instagram page Brent Council's LinkedIn site Brent council's Twitter feed Brent council's YouTube channel
Accessibility statement Cookies policy Privacy policy Terms of use
© Copyright Brent Council 2022

Title