Park Lane Primary School
Decision Maker: Executive
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To approve to delegate authority to the Director of Regeneration and Major Projects to appoint a works contractor using the IESE construction Framework Agreement, for the expansion project at Park Lane Primary School.
Decision:
(i) that the increase in scheme costs by £400,000 from £2.2m to 2.6m be noted, and that this will be funded from the Schools Main Capital Programme at £1m and £1.6m is to be resourced from BNSV monies;
(ii) that authority be delegated to the Director of Regeneration and Major Projects to appoint and award a contract to the preferred ‘Contractor A’, who is named in Appendix 3 to the Director’s report and is a contractor from the IESE Framework Agreement in relation to the construction works at Park Lane Primary School, to not exceed £2.35m, subject to an adjustment as considered necessary to the Main Capital Programme, in accordance with the needs of other schools expansion projects on this resource and with the agreement of the Director of Finance and Corporate Services.
Wards Affected: (All Wards);
Other reasons / organisations consulted
Internal
Contact: Christine Moore, Property and Asset Management Email: christine.moore@brent.gov.uk Tel: 020 8937 3118.
Report author: Christine Moore, Krutika Pau
Publication date: 13/04/2011
Date of decision: 11/04/2011
Decided at meeting: 11/04/2011 - Executive
Accompanying Documents:
- park-lane PDF 113 KB
- park-lane-app1 PDF 36 KB
- park-lane-app4 PDF 85 KB
- Restricted enclosure View reasons restricted
- Restricted enclosure View reasons restricted
- Restricted enclosure View reasons restricted