Decision details
Street Lighting: Energy and Carbon Saving Proposals - authority to tender
Decision Maker: Cabinet
Decision status: Recommendations Approved
Is Key decision?: Yes
Is subject to call in?: No
Purpose:
To approve proposals to reduce energy consumption and carbon emissions from street lighting through the installation of LED lighting and associated systems; and authorise the joint invite of tenders with PFI Partners for the supply and installation of lighting technologies, as required by Contract Standing Orders 85, 88 and 89.
Decision:
(i) that the business case for investment in LED (Light Emitting Diode) luminaires, be endorsed for the reasons outlined in section 3 of the report, and officers be authorised to commence the procurement of LED luminaires with reference to the pre-tender considerations outlined in paragraph 6 of the report;
(ii) that the business case for investment in Central Management System (CMS), be endorsed for the reasons outlined in section 3 of the report, and officers be authorised to commence the procurement of CMS with reference to the pre-tender considerations outlined in Part 6 of this report;
(iii) that approval be given to the invite of tenders for the supply of LED and CMS on the basis of the pre-tender considerations set out in paragraph 6.1 of the report, and authority given to tendering in partnership with PFI Lighting Ltd, noting the issues set out in sections 4 and 5 of the report;
(iv) that officers and their PFI partners evaluate the tenders referred to in (iii) above on the basis of the evaluation criteria set out in paragraph 6.1 of the report, with a further report to Cabinet following the tender exercise which will make recommendations on the award of Contract;
(iv) that officers develop a new lighting strategy, specifically facilitated by the deployment of CMS technology, which would seek further energy and carbon savings whilst meeting the long-term lighting needs of the borough.
Reason Key: Affects more than 2 wards;
Wards Affected: (All Wards);
Contact: Gavin F Moore, Head of Parking and Lighting Email: gavin.f.moore@brent.gov.uk Tel: 020 8937 2979.
Report author: Andrew Clarke
Publication date: 17/04/2015
Date of decision: 14/04/2015
Decided at meeting: 14/04/2015 - Cabinet