07/07/2020 - Authority to Award a Contract for boiler replacement works at Roe Green Infant and Junior Schools and Wykeham Primary School ref: 5090 Recommendations Approved
To request approval to award a contract for
boiler replacement works at Roe Green Infant and Junior Schools and
Wykeham Primary School as per Contract Standing Order 88.
Decision Maker: Director - Property and Assets
Decision published: 08/07/2020
Effective from: 16/07/2020
Decision:
That the Operational Director, Property & Assets:
i) Approves the award of a contract for boiler replacement works at Roe Green Infant and Junior Schools and Wykeham Primary School to BSW Heating Ltd for £336,908.
Wards affected: Queensbury; Welsh Harp;
Lead officer: Nick Ljustina
07/07/2020 - Authority to Award a Contract for roof renewal and structural works project at Uxendon Manor Primary School ref: 5091 Recommendations Approved
To request approval to award a contract in
respect of a contract for the roof renewal and structural works
project at Uxendon Manor Primary School as per Contract Standing
Order 88
Decision Maker: Director - Property and Assets
Decision published: 08/07/2020
Effective from: 16/07/2020
Decision:
That the Operational Director, Property & Assets:
i) Approves the award of a contract for the roof renewal and structural works project at Uxendon Manor Primary School to CWG Roofing Ltd. for £291,037.
Wards affected: Kenton;
Lead officer: Nick Ljustina
07/07/2020 - Award of contract for delivery of heating distribution and emitter works at Mount Stewart Infant School and Boiler Replacement and associated plant at Lyon Park Primary School ref: 5089 Recommendations Approved
This decision seeks approval to the award of a contract for delivery of heating distribution and emitter works at Mount Stewart Infant School and Boiler Replacement and associated plant works at Lyon Park Primary School.
Decision Maker: Director - Property and Assets
Decision published: 08/07/2020
Effective from: 16/07/2020
Decision:
That the Operational Director, Property & Assets:
i) Approves the award of a contract for the delivery of heating distribution and emitter works at Mount Stewart Infant School and boiler replacement and associated plant works at Lyon Park Primary School to GS James Mechanical Services Ltd. for £580,900.
Wards affected: Alperton; Kenton;
Lead officer: Neil Martin
07/07/2020 - Authority to Award a Contract for pitched roof replacement, window replacement and structural repairs at Mora Primary School ref: 5088 Recommendations Approved
To request approval to award a contract for
pitched roof replacement, window replacement and structural repairs
at Mora Primary School as per Contract Standing Order 88.
Decision Maker: Director - Property and Assets
Decision published: 08/07/2020
Effective from: 16/07/2020
Decision:
That the Operational Director, Property & Assets:
i) Approves the award of a contract for pitched roof replacement, window replacement and structural repairs at Mora Primary School to Gunite Eastern Ltd for £527,217.
Wards affected: Kenton;
Lead officer: Nick Ljustina
01/07/2020 - Local Authority Discretionary Grant Scheme criteria expansion (Emergency Non-Key Decision) ref: 5086 Recommendations Approved
Approval is being sought to agree the expansion of the Local Authority Discretionary Grant Scheme criteria as outlined in paragraph 3.12 and Appendix 2 of the accompanying report and to note that the deadline for the scheme is now extended indefinitely until the funds have been spent.
Decision Maker: Chief Executive
Decision published: 02/07/2020
Effective from: 01/07/2020
Decision:
That the Chief Executive exercises her urgency powers to agree the expansion of the Local Authority Discretionary Grant Scheme criteria as outlined in paragraph 3.12 and Appendix 2 of the report and notes that the deadline for the scheme is now extended indefinitely until the funds have been spent.