Issue details
Extension of Communal Electrical Works and Electrical Safety Maintenance Contract
To request approval to vary the contract for Communal Electrical Works and Electrical Safety Maintenance to permit the extension of the contract, and approval to extend the contract for a period of 12 months.
Decision type: Key
Reason Key: Signficant expenditure/savings of £500k or more;
Decision status: Recommendations Approved
Wards affected: (All Wards);
Notice of proposed decision first published: 31/01/2023
Anticipated restriction: Part exempt - View reasons
Explanation of anticipated restriction:
Extension of existing contract pending the procurement of a replacement contract.
Decision due: Not before 1 Mar 2023 by Director - Housing Services
Lead member: Cabinet Member for Housing
Lead director: Director - Housing Services
Department: Partnerships, Housing & Residents Services
Contact: Giuseppe Coia, Major Works and Refurbishments Manager Email: Giuseppe.Coia@brent.gov.uk Tel: 020 8937 2652.