Issue details
Uxendon Manor Primary School Expansion Project: Update and Request for Budget Increase
To note the increased project costs; approve a virement; note the revised procurement strategy along with the intention to pursue a claim through a commercial settlement against the contractor’s Parent Company Guarantee (PCG).
Decision type: Key
Reason Key: Signficant expenditure/savings of £500k or more;
Decision status: Recommendations Approved
Wards affected: Kenton;
Notice of proposed decision first published: 08/11/2019
Anticipated restriction: Part exempt - View reasons
Explanation of anticipated restriction:
Part Exempt - Appendix 1 is not for publication as it contains the following category of exempt information as specified in Paragraph 3, Schedule 12A of the Local Government Act 1972, namely: “Information relating to the financial or business affairs of any particular person (including the authority holding that information).
Decision due: 9 Mar 2020 by Cabinet
Lead member: Cabinet Member for Jobs, Economy & Citizen Experience
Lead director: Strategic Director - Regeneration and Environment
Department: Regeneration and Environment
Contact: Cheryl Andani, Programme Manager, Inward Inestment and Capital Delivery Email: cheryl.andani@brent.gov.uk Tel: 020 8937 3227.
Decisions
- 10/03/2020 - Uxendon Manor Primary School Expansion Project
Agenda items
- 09/03/2020 - Cabinet Uxendon Manor Primary School Expansion Project 09/03/2020
Documents
- Uxendon Manor Primary School Expansion Project: Update and Request for Budget Increase