Authority to vary contract in respect of design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction & Infrastructure Ltd (non-key officer recordable decision)
14/11/2025 - Authority to vary contract in respect of design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction & Infrastructure Ltd (non-key officer recordable decision)
That the Director of Property and Assets:
i) Approves the variation of the contract for the design and build of the Additionally Resourced Provision (ARP) at St Margaret Clitherow RC Primary School with Morgan Sindall Construction Ltd by $488,606.12 to deal with unforeseen ground conditions, asbestos removal and external works.