Issue - decisions
Authority to Vary Contract in Respect of Design and Build of the Additionally Resourced Provision (ARP) at Newman Catholic College with Morgan Sindall Construction & Infrastructure Ltd (Non-Key Officer Recordable Decision)
12/09/2025 - Authority to Vary Contract in Respect of Design and Build of the Additionally Resourced Provision (ARP) at Newman Catholic College with Morgan Sindall Construction & Infrastructure Ltd (Non-Key Officer Recordable Decision)
That the Director Property and Assets:
i) Approves the variation of the contract for the design and build of the Additionally Resourced Provision (ARP) at Newman Catholic College with Morgan Sindall Construction & Infrastructure Ltd by £375,447.11 to deal with unforeseen ground conditions, asbestos removal and additional school requirements.