High Rise Major Works and Energy Efficiency Programme 2023 - 2026
14/12/2022 - High Rise Major Works and Energy Efficiency Programme 2023 - 2026
Cabinet RESOLVED:
(1) To approve the variation to the contract with Wates Construction Limited for the Integrated Asset Management, Planned and Cyclical Maintenance and Responsive Repairs Maintenance Works (“IAM Contract”) to allow for the reinstatement of the undertaking of major works.
(2) To delegate the commission of a works contract for those matters detailed in Section 4 of the report from the IAM contract to the Corporate Director of Resident Services in consultation with the Cabinet Member for Housing, Homelessness & Renters Security.
(3) To approve an extension of the IAM contract in connection only with the works detailed in (2) above that had an approximate completion date of Spring 2025.