Cabinet RESOLVED:
(1) To approve the procurement of a delivery partner for the NWCC site including, 1-8 Neville House, 1-64 Winterleys, 113-128 Carlton House and Carlton Hall; through inviting tenders using a Competitive Procedure with Negotiation under the Public Contracts Regulations 2015.
(2) To approve the procurement of delivery partners/contractors for the remaining Phases (3b-8) of the South Kilburn Programme sites.
(3) To delegate authority to the Strategic Director of Regeneration & Environment in consultation with the Lead Member of Regeneration, Property and Planning, to select the appropriate procurement route and pre-tender considerations for those remaining sites within Phases 3b-8 and to evaluate such tenders.
(4) To delegate to the Strategic Director of Regeneration and Environment in consultation with the Lead Member Regeneration, Property and Planning authority to award the contract for Delivery Partners to progress the comprehensive redevelopment of the remaining sites from Phase 3b-8 within the South Kilburn Programme.
(5) To delegate to the Strategic Director of Regeneration and Environment in consultation with the Lead Member Regeneration, Property and Planning the decision on alternative development routes if procurement was unsuccessful in relation to the remaining sites from Phase 3b-8 within the South Kilburn Programme.
(6) To approve the setting of rent levels for the affordable homes at all remaining sites within the Programme (Phases 3b-8) at the South Kilburn Social rent levels.
(7) To approve capital funding (strategic community infrastructure levy) of £4.9m to deliver the infrastructure and public realm works within the NWCC Project.