Authority to award the works contracts for the Design and Build of Phase 3 Primary School Expansion Projects
12/04/2016 - Authority to award the works contracts for the Design and Build of Phase 3 Primary School Expansion Projects
(1) Byron Court Primary School
(i) Delegate authority to make the final decision to award the two stage design and build contract for the expansion of Byron Court Primary School to Morgan Sindall Group to the Strategic Director of Regeneration and Environment in consultation with the Chief Legal Officer and Chief Finance Officer following successful completion of all associated matters including planning approval. The first stage of the contract (Preconstruction Services Agreement) to commence following award;
(ii) Delegate authority to trigger the entry into the stage two main works contract to the Strategic Director of Regeneration and Environment in consultation with the Chief Legal Officer and Chief Finance Officer following successful conclusion of the Pre Construction Services Agreement.
(2) Elsley Primary School
(i) Subject to planning approval detailed in paragraph 3.4 and table 2, award the two stage design and build contract for the expansion of Elsley Primary School to Lakehouse Contracts Ltd with the first stage of the contract (Preconstruction Services Agreement) to commence following award.
(ii) Subject to planning approval detailed in paragraph 3.4 and table 2, award the fixed cost lump sum works contract (contract 1) to Lakehouse Contracts Ltd
(iii) Delegate authority to trigger entry into the stage two main works contract to the Strategic Director of Regeneration and Environment in consultation with the Chief Legal Officer and Chief Finance Officer following successful conclusion of the Preconstruction Services Agreement.
(3) The Stonebridge Primary School
(i) Subject to planning approval detailed in paragraph 3.4 and table 2, award the two stage design and build contract for the expansion of The Stonebridge Primary School to Morgan Sindall Group with the first stage of the contract (Preconstruction Services Agreement) to commence following award.
(ii) Delegate authority to trigger entry into the stage two main works contract to the Strategic Director of Regeneration and Environment in consultation with the Chief Legal Officer and Chief Finance Officer following successful conclusion of the Preconstruction Services Agreement.
(4) Uxendon Manor Primary School
(i) Award the two stage design and build contract for the expansion of Uxendon Manor Primary School to Morgan Sindall Group with the first stage of the contract (Preconstruction Services Agreement) to commence following award.
(ii) Delegate authority to trigger entry into the stage two main works contract to the Strategic Director of Regeneration and Environment in consultation with the Chief Legal Officer and Chief Finance Officer following successful conclusion of the Preconstruction Services Agreement.