2015/16 Temporary Expansion Programme
29/07/2015 - 2015/16 Temporary School Expansion Programme
(i) that the projected demand for primary school places in 2015/16 alongside the planned capacity be noted:
(ii) that approval be given to the 2015/16 Temporary School Expansion Programme as described in paragraphs 3.9-3.12;
(iii) that approve be given to the budget of £2.148m for the 2015/16 Temporary School Expansion Programme to be met from secured Basic Need Funding within the Schools Capital Portfolio;
(iv) that approval the continued use of council buildings to meet the required number of school places across the borough as described in paragraphs 3.15-3.16 and to delegate authority for the Operational Director – Property & Projects to enter into necessary licences for use with the managing schools.