School Expansion Programme - temporary primary school expansion 2013/14 and Preston Manor School
18/07/2013 - School Expansion Programme - temporary primary school expansion 2013/14 and Preston Manor School
(i) that the current status of all projects to provide temporary school places for September 2013 and during the 2013/14 academic year be noted;
(ii) that approval be given to the use of Anansi to provide temporary school places for three to five years aligning with Knowles House temporary use arrangements and to agree that an appropriate lease/license agreement be entered into with College Green Nursery allowing occupation;
(iii) that approval be given to the use of Douglas Avenue to provide temporary classes for up to two years and to agree that an appropriate lease/licence agreement be entered into with a suitable school to allow occupation;
(iv) that the use of Strathcona to provide temporary classes for four to seven years, thus withdrawing the site from the market for that period be authorised and to agree that an appropriate lease/licence agreement be entered into with Roe Green Infant School to allow occupation;
(v) that authority be delegated to the Operational Director Property and Projects to agree the terms of the lease/license and enter into appropriate agreements;
(vi) that the current status of the legal process in relation to the restrictive covenants on land belonging to Preston Manor School be noted;
(vii) that approval be given to the continuation of the Upper Tribunal process in relation to the covenants related to Preston Manor School.