20/2784 Northfields, Beresford Avenue, Wembley, HA0 1NW (Known as "Grand Union")
Meeting: 10/02/2021 - Planning Committee (Item 3)
3 20/2784 Northfields, Beresford Avenue, Wembley, HA0 1NW (Known as "Grand Union") PDF 813 KB
Additional documents:
- 20.2784 SUPP Northfields, item 3 PDF 106 KB
- Webcast for 20/2784 Northfields, Beresford Avenue, Wembley, HA0 1NW (Known as "Grand Union")
Decision:
Granted planning permission, subject to the legal agreement and conditions and informatives as set out in the original committee report, and referral of the application to the Mayor of London for his Stage 2 response.
Minutes:
PROPOSAL:
Hybrid planning application comprising:-
Outline planning permission for the demolition of existing buildings and structures on the site, all site preparation works and redevelopment to provide new buildings to accommodate new homes (Use Class C3), flexible commercial uses, new basement level, associated cycle and vehicle parking, new vehicular accesses, associated highway works to Beresford Avenue, landscaping and creation of new public and private open space, ancillary facilitating works, various temporary meanwhile uses, interim works and infrastructure with all matters reserved - appearance, access, landscaping, layout and scale.
Detailed planning permission for Phase 3 (Buildings G, H and J) for the demolition of existing buildings and structures, all site preparation and infrastructure works and the development of new homes (Use Class C3) and flexible commercial floorspace; together with new basement level, associated storage, cycle and vehicle parking, new vehicular accesses, associated highway works to Beresford Avenue, landscaping and creation of new public and private open space, ancillary facilitating works.
RECOMMENDATION:
To resolve to grant planning permission, subject to the Stage 2 referral to the Mayor of London and subject to the completion of a satisfactory Section 106 or other legal agreement to secure the matters set out within the reports, the conditions and informatives recommended in this report, and to delegate authority to the Head of Planning or other duly authorised person to agree the exact terms thereof on advice from the Chief Legal Officer.
That the Head of Planning is granted delegated authority to negotiate the legal agreement indicated above.
That the Head of Planning is granted delegated authority to issue the planning permission and impose conditions to secure the matters set out within the reports.
Messrs Colin Leadbeatter, Neil Quinn and Liam McFadden (Principal Planning Officers) introduced the report, set out the key issues and answered Members’ questions. In reference to the supplementary report, Mr Leadbeatter drew the following salient matters of clarification to Members’ attention:
· The number of dual aspect homes would be increased to 61% within Phase 3 of the development, rather than across the outline consent.
· The financial contribution secured under the original s106 agreement for improvements to Stonebridge Park station would be £2m not £4.6m stated.
· To clarify, £4.6m was secured towards bus service enhancements under the original s106 agreement.
· All trees and hedgerows have already removed under the extant Masterplan consent.
He then outlined the various phases of the revised Masterplan that now included additional 330 homes with commensurate increase in affordable homes (35%), compliant with the emerging housing policy. Members heard about additional communal space provisions, improvements to public open space, provision of community centre and a nursery, significantly higher landscaping and CIL contributions of £73million.
Ms Claire Hammond (Land Director of the applicant St George) addressed the Committee and answered Members’ questions on several matters including mix of tenure, affordable homes, traffic and parking. She provided the following updates on the delivery of the proposed development:
· Phase 1 of the scheme, well advanced, would provide 400 homes of which 114 ... view the full minutes text for item 3