Approval to terminate the high value works contract for the expansion of Elsley Primary School
Meeting: 15/04/2019 - Cabinet (Item 11)
11 Expansion of Elsley Primary School - Termination of Design and Build Contract PDF 97 KB
The report provides Cabinet with an update on the contractual position on the design and build contract for the expansion of Elsley Primary School and seeks authority to terminate the existing design and build contract.
Additional documents:
- 11a. NOT FOR PUBLICATION - Appendix 1 , View reasons restricted (11/2)
Decision:
RESOLVED:
i. Cabinet noted the current status and contractual position with Lakehouse Contracts Limited on the design and build contract for Elsley Primary School as set out in the report.
ii. Cabinet approved the termination of the High Value Works Contract with Lakehouse Contracts Limited for expansion of Elsley Primary School.
iii. Cabinet noted that subject to Recommendation 2.2 set out in the report, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts to enable outstanding works to be completed using powers delegated under the Constitution.
iv. Cabinet noted that the school was and would continue to be operational whilst the steps outlined in the report recommendations be taken.
v. Cabinet noted that Officers would review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited as described in Appendix 1.
Minutes:
RESOLVED:
i. Cabinet noted the current status and contractual position with Lakehouse Contracts Limited on the design and build contract for Elsley Primary School as set out in the report.
ii. Cabinet approved the termination of the High Value Works Contract with Lakehouse Contracts Limited for expansion of Elsley Primary School.
iii. Cabinet noted that subject to Recommendation 2.2 set out in the report, the Strategic Director of Resources would approve the award of one or more Low and/or Medium Value Works Contracts to enable outstanding works to be completed using powers delegated under the Constitution.
iv. Cabinet noted that the school was and would continue to be operational whilst the steps outlined in the report recommendations be taken.
v. Cabinet noted that Officers would review options for the recovery of any wasted or additional costs against Lakehouse Contracts Limited as described in Appendix 1.