Issue - meetings
Phase 2 Carlton & Granville Enterprise Hub
Meeting: 13/11/2017 - Cabinet (Item 11)
This report provides an update to the 15 November 2016 Cabinet report – South Kilburn Regeneration Programme – Carlton & Granville Centres Site – Development Options. This report seeks approval to progress with appointment of a Design Team for Phase 2 of Carlton and Granville Centres Development as required by Contract Standing Order 88.
Additional documents:
- Appendix 1 - Restricted , View reasons restricted (11/2)
- Appendix 2 - Tender Award Report, item 11 PDF 111 KB
Decision:
RESOLVED:
11.1 The redevelopment of Carlton and Granville Centres site as Phase 2 of the works be awarded to an architecturally led multidisciplinary design team;
11.2 Authority be delegated to the Strategic Director of Regeneration & Environment in consultation with the Cabinet Member for Regeneration and Employment to oversee design development through further viability testing, local consultation and ultimately agree the scheme that is submitted for planning approval; and
11.3 Authority be delegated to the Strategic Director of Regeneration & Environment to proceed with RIBA Stage 4 and surveys and assessments as outlined in Appendix 2 to the Cabinet report.
Minutes:
Councillor Shama Tatler, Cabinet Member for Regeneration, Growth, Employment and Skills, introduced the report providing an update to the 15 November 2016 Cabinet report – South Kilburn Regeneration Programme – Carlton & Granville Centres Site – Development Options.
Councillor Tatler stated that the report seeks approval to progress with appointment of a Design Team for Phase 2 of Carlton and Granville Centres Development as required by Contract Standing Order 88.
RESOLVED:
11.1 The redevelopment of Carlton and Granville Centres site as Phase 2 of the works be awarded to an architecturally led multidisciplinary design team;
11.2 Authority be delegated to the Strategic Director of Regeneration & Environment in consultation with the Cabinet Member for Regeneration and Employment to oversee design development through further viability testing, local consultation and ultimately agree the scheme that is submitted for planning approval; and
11.3 Authority be delegated to the Strategic Director of Regeneration & Environment to proceed with RIBA Stage 4 and surveys and assessments as outlined in Appendix 2 to the Cabinet report.