Chippenham Gardens, South Kilburn - To seek approval to use an appropriate Framework or OJEU process to procure a delivery partner together with an update on project issues and options

  • Issue Details
  • Issue History
  • Related Decisions
  • Related Meetings
 

 

Meeting: 19/06/2017 - Cabinet (Item 8)

8 Chippenham Gardens (Land North) South Kilburn pdf icon PDF 146 KB

This report relates to Chippenham Gardens, which is a fundamental part of the South Kilburn Regeneration Programme. The report provides Cabinet with an update on the Chippenham Gardens project and seeks approval for the procurement of a delivery partner and to set rent levels at Homes and Communities Agency Target Rent. It also notes the eventual intent to buy out the land owner of 5-9 Chippenham Gardens, Kilburn Park Post Office (see appendix 2). This report also updates Cabinet on the current position of the negotiations with the remaining leaseholders and the possible need to rely on the exercise of Compulsory Purchase Order (CPO) powers in order to obtain vacant possession.

Additional documents:

  • Appendix 1 - Chippenham Gardens Red Line Plan, item 8 pdf icon PDF 405 KB
  • Appendix 2 - Land North of Chippenham Gardens, item 8 pdf icon PDF 166 KB
  • Appendix 3 - Requirement and Responses, item 8 pdf icon PDF 284 KB

Decision:

RESOLVED:

 

8.1      Cabinet approved the procurement of a delivery partner for the Chippenham Gardens site either through a mini-competition using an appropriate Framework or alternatively through a Competitive Procedure with Negotiation under the Public Contracts Regulations 2015 on the basis of the pre-tender considerations set out in Appendix 3 of the report from the Strategic Director of Regeneration & Environment and evaluating the tenders on the basis of the evaluation criteria set out in Appendix 3.

 

8.2      Cabinet agreed to delegate to the Strategic Director of Regeneration & Environment in consultation with the Lead Member of Regeneration, Growth, Employment and Skills, authority to select the appropriate procurement route outlined in 8.1 above for the reasons detailed in paragraph 3.8 of the report from the Strategic Director of Regeneration & Environment.

 

8.3      Cabinet approved the setting of rent levels for the affordable homes at the Chippenham Gardens site once complete, at a rent equivalent to the H.C.A. Target Rent levels.

 

8.4      Cabinet approved in principle the proposal to buy out the landowner of 5-9 Chippenham Gardens, Kilburn Park Post Office.

 

8.5      Cabinet noted the possible need to rely on the exercise of CPO powers to obtain vacant possession should an agreement not be reached with the remaining leaseholders and the continuing efforts by officers to reach an amicable agreement with the remaining leaseholders.

Minutes:

Councillor Sharma Tatler, Cabinet Member for Regeneration, Growth, Employment and Skills, introduced the report regarding the Chippenham Gardens site, a fundamental part of the South Kilburn regeneration programme. Approval was sought for the procurement of a delivery partner to speed up delivery timescales and to set rent levels at Homes and communities Agency Target Rent.

 

RESOLVED:

 

8.1      Cabinet approved the procurement of a delivery partner for the Chippenham Gardens site either through a mini-competition using an appropriate Framework or alternatively through a Competitive Procedure with Negotiation under the Public Contracts Regulations 2015 on the basis of the pre-tender considerations set out in Appendix 3 of the report from the Strategic Director of Regeneration & Environment and evaluating the tenders on the basis of the evaluation criteria set out in Appendix 3.

 

8.2      Cabinet agreed to delegate to the Strategic Director of Regeneration & Environment in consultation with the Lead Member of Regeneration, Growth, Employment and Skills, authority to select the appropriate procurement route outlined in 8.1 above for the reasons detailed in paragraph 3.8 of the report from the Strategic Director of Regeneration & Environment.

 

8.3      Cabinet approved the setting of rent levels for the affordable homes at the Chippenham Gardens site once complete, at a rent equivalent to the H.C.A. Target Rent levels.

 

8.4      Cabinet approved in principle the proposal to buy out the landowner of 5-9 Chippenham Gardens, Kilburn Park Post Office.

 

8.5      Cabinet noted the possible need to rely on the exercise of CPO powers to obtain vacant possession should an agreement not be reached with the remaining leaseholders and the continuing efforts by officers to reach an amicable agreement with the remaining leaseholders.


 

Navigation

  • Issue - items at meetings - Chippenham Gardens, South Kilburn - To seek approval to use an appropriate Framework or OJEU process to procure a delivery partner together with an update on project issues and options
  • What's new
  • Committees
  • Constitution
  • Calendar
  • Meetings
  • Committee decisions
  • Officer Decisions
  • Forward plans
  • Your Councillors
  • Your MPs
  • Election Results
  • Outside bodies
  • Search documents
  • Subscribe to updates
Brent homepage
Your council
Complaints and feedback Contact the council Jobs at the council News and Press office Sign up to our weekly email news updates
My Account
Manage your Council Tax, housing benefits, council rent account and more through My Account.
Sign in or register
Follow us on social
Brent Council's Facebook page Brent's Instagram page Brent Council's LinkedIn site Brent council's Twitter feed Brent council's YouTube channel
Accessibility statement Cookies policy Privacy policy Terms of use
© Copyright Brent Council 2022

Title