South Kilburn Enterprise Hub
Meeting: 25/07/2016 - Cabinet (Item 9)
This report updates members on proposals to deliver a new Enterprise Hub and proposes the re-development of the Carlton and Granville Centres as a location for the Enterprise Hub and deliver 95 new home with additional community space.
Decision:
(i) that approval be given to Option 2 for redeveloping the Carlton & Granville Centres, Granville Road, London, NW6 5RA (the subject site) to deliver 95 new homes, an Enterprise Hub and 3274sqm of additional community use space;
(ii) that a further update be provided to formally approve final scheme plans and the required capital investment to bring forward the phased redevelopment of the Carlton and Granville Centres and ensure continuity of occupation for the Enterprise Hub within the site;
(iii) that the site be included within the scope of the South Kilburn Masterplan review to ensure wider place making considerations are incorporated;
(iv) that the Strategic Director for Resources in consultation with the Strategic Director for Regeneration and Environment, Chief Legal Officer and Chief Finance Officer enter into a legal agreement with the South Kilburn Trust and the GLA to secure their funding contributions in return for project delivery of the Enterprise Hub by March 2018, and setting out Council commitment to underwrite the shortfall in project funds;
(v) that authority be delegated to the Strategic Director for Resources in consultation with the Strategic Director for Regeneration and Environment, Chief Legal Officer and Chief Finance Officer to oversee scheme development through further viability testing, local consultation, and planning consent;
(vi) that authority be delegated to the Strategic Director for Resources in consultation with the Strategic Director for Regeneration and Environment, Chief Legal Officer and Chief Finance Officer in respect to any works and/or professional services contracts for scheme development to agree pre-tender considerations, invite tenders and thereafter award the contract.
Minutes:
Councillor McLennan, Deputy Leader of the Council, introduced the report. She informed members that the Cabinet had approved the Strategic Property Plan 2015-19 setting out a presumption for Brent to retain its limited property assets, utilising them to support regeneration, generating revenue savings, and capital investment for new income generation.
Councillor McLennan stated that in January 2016 Brent had successfully secured £1.8m from the London Regeneration Fund (LRF) which was matched funded with a further £2m (£1.5m capital & £500k revenue) from the South Kilburn Trust (SKT) to deliver a new Enterprise Hub as part of addressing the lack of good quality, small workspace provision in the borough and provide a permanent location for the South Kilburn Trust to continue to deliver services and support to the local community within South Kilburn.
She stated that the report updated members on proposals to deliver a new Enterprise Hub and proposed the re-development of the Carlton and Granville Centres as a location for the Enterprise Hub and deliver 95 new homes with additional community space.
RESOLVED:
(i) that approval be given to Option 2 for redeveloping the Carlton and Granville Centres, Granville Road, London, NW6 5RA (the subject site) to deliver 95 new homes, an Enterprise Hub and 3274sqm of additional community use space;
(ii) that a further update be provided to formally approve final scheme plans and the required capital investment to bring forward the phased redevelopment of the Carlton and Granville Centres and ensure continuity of occupation for the Enterprise Hub within the site;
(iii) that the site be included within the scope of the South Kilburn Masterplan review to ensure wider place making considerations are incorporated;
(iv) that the Strategic Director for Resources in consultation with the Strategic Director for Regeneration and Environment, Chief Legal Officer and Chief Finance Officer enter into a legal agreement with the South Kilburn Trust and the GLA to secure their funding contributions in return for project delivery of the Enterprise Hub by March 2018, and setting out council commitment to underwrite the shortfall in project funds;
(v) that authority be delegated to the Strategic Director for Resources in consultation with the Strategic Director for Regeneration and Environment, Chief Legal Officer and Chief Finance Officer to oversee scheme development through further viability testing, local consultation, and planning consent;
(vi) that authority be delegated to the Strategic Director for Resources in consultation with the Strategic Director for Regeneration and Environment, Chief Legal Officer and Chief Finance Officer in respect to any works and/or professional services contracts for scheme development to agree pre-tender considerations, invite tenders and thereafter award the contract.