Issue - meetings
South Kilburn Regeneration Programme
Meeting: 14/03/2016 - Cabinet (Item 9)
9 South Kilburn Regeneration Programme - Phase 4 notices PDF 97 KB
This report summarises the progress made on the regeneration of South Kilburn and sets out the approvals required by the Cabinet to further progress Phase 4 of the regeneration programme.
Additional documents:
Decision:
(i) that the progress made to date in delivering the South Kilburn Regeneration as detailed in the submitted report at Appendix 1 be noted;
(ii) that the serving of demolition notices and the suspension of secure tenants’ Rights to Buy in relation to secure tenancies in blocks Dickens House, Blake Court, Crone, Zangwill and John Ratcliffe House (together defined as ‘Phase 4B’ of the South Kilburn regeneration programme) be authorised and the Strategic Director of Regeneration and Environment be authorised to issue all and any notices required to be issued in connection with such demolition.
Minutes:
Councillor McLennan, Cabinet Member for Housing and Development, introduced the report summarising the progress made on the regeneration of South Kilburn and setting out the approvals required by the Cabinet to further progress Phase 4 of the regeneration programme.
She indicated that the report set out the approvals required by the Cabinet to serve demolition notices on Phase 4B of the South Kilburn regeneration programme (being Dickens House, Blake Court, Crone, Zangwill and John Ratcliffe House). This would enable the next major phase of the Regeneration programme to be initiated.
Councillor Duffy, Kilburn Ward, welcomed the report and agreed to meet with Councillor McLennan to discuss publicity and consultation in the area.
RESOLVED:
(i) that the progress made to date in delivering the South Kilburn Regeneration as detailed in the submitted report at Appendix 1 to the report be noted;
(ii) that the serving of demolition notices and the suspension of secure tenants’ Rights to Buy in relation to secure tenancies in blocks Dickens House, Blake Court, Crone, Zangwill and John Ratcliffe House (together defined as ‘Phase 4B’ of the South Kilburn regeneration programme) be authorised and the Strategic Director of Regeneration and Environment be authorised to issue all and any notices required to be issued in connection with such demolition.