John ChristieSummary
The report sets out an update on the proposals for setting up the
second City Academy (Wembley Park Academy – an operational
name) and seeks Executive approval to proceed to develop the scheme
to Outline Business Case. This report also offers a preview of the
procurement process (able to start in February 2008) as outlined in
Paragraphs 4.1 to 4.16 in the context of the risks set out in
Paragraphs 6.5 to 6.7 and in Attachment A and seeks approval in
principle to the Council procuring the buildings for the Wembley
Park Academy.Related reports
C&F 2nd Academy Update Att A - risk
trans.pdf;C&F 2nd Academy Update Att B - articles of
gov.pdf;C&F 2nd Academy Update Att C - ARK gen gov.pdf;C&F
2nd Academy Update App D - glossary.pdf;C&F 2nd Academy Update
Att E - delivery.pdf;C&F 2nd Academy Update - Attachment F -
Funding Bid.pdf